Have a question about a project? Visit our Contact Form.

Upcoming Projects: In Planning or Under Construction

Parking Lot and Roadway Improvements

Tentative Schedule:

  • Independence Street and parking lot west of the street (leading to Foothills Fieldhouse and Jason Jennings Adaptive Field) – completed July 2025
  • Peak Community & Wellness Center parking lots – completed August 2025
  • Clement Park, eastern side parking lots and some roadway areas – estimated completion, fall 2025.
  • Schaefer Athletic Complex – estimated completion, fall 2025
  • Foothills Golf Maintenance Access Road – estimated completion, winter fall 2025

Back to top

Mechanical & Electrical Upgrades (multiple locations)

Improvements Description: Replace and install equipment in a variety of facilities to enhance energy efficiency and improve aging mechanical systems.

Back to top

2025 Completed Projects

Dutch Creek Regional Trail

Completed: September 2025

Community Outreach:

  • Virtual meeting was held Tuesday, February 10, 2022
  • Open House was held Wednesday, March 30, 2022
  • Trail design completed in March 2023.
  • County permitting process and approval required before work can begin.  Permit obtained in 2024.
  • Construction bidding completed spring 2024.
  • Construction began in spring 2024 with completion in 2025.
  • View Map of Dutch Creek Trail

Improvements Description: Extend the existing trail from just west of Kipling and connect it to the C-470 Trail. This project provides safer and more convenient connectivity for all trail users to other regional trails such as the C-470 Trail and the Mary Carter Greenway Trail.  This project was completed with proceeds from the voter approved 2020 mill levy continuation, a $1.86 million grant from the Jefferson County Open Space Trails Partnership Program, and a $3,000 donation from the Foothills Foundation.

History: Previous to the project completion, the section of the Dutch Creek Trail that Foothills Park & Recreation District managed runs largely to the south of W. Coal Mine Avenue from S. Pierce Street (to the east) and ended just west of Kipling.

Back to top

Easton Regional Park

Completed: Winter 2025, will open to the public in 2026

Improvements Description: New ballfield in the northwest section of the park and improved the core area between the ballfields including improved access, drainage improvements, seating and bleacher improvements, shade, new tree plantings.

History: The original park site, Waters Edge, was dedicated to Foothills in the late 1980s. Jefferson County Open Space purchased the remainder of the site in 1992 and later it was developed by Foothills into Easton Regional Park.

Back to top

Aerial view of new, third ballfield added to the Easton Regional Park as well as improvements to the plaza between the three ball fields.

Foothills Fieldhouse

  • Upgraded cooling system, completed June 2025
  • Replaced synthetic turf, completed September 2025

Back to top

Lakehurst West Park

Completed: February 2025

Improvements Description: New amenities added to the site including a small playground, benches and a short walkway to playground.

Community Outreach: Concept plans for the park and for the playground were provided to the community.

History: This park was dedicated to Foothills in 1992 through Senate Bill 35 land dedication requirements.

Back to top

Sgt. Timothy M. Mossbrucker Park

Completed: September 2025, opening to the public mid-late September 2025

Improvements Description: Playground replacement

Community Outreach: This project has been community-focused from the very beginning. Planning staff partnered with third graders at Mt. Carbon Elementary to help design the playground and more than 500 community members and students voted in a playground survey to pick the playground. The winning design was presented back to the student designers, the school and shared with the broader community, ensuring that the project truly reflects the voices of those who will use the space.

On playground build day, we were joined by a group of volunteers from The Church of Jesus Christ of Latter-day Saints. Members of the Foothills Foundation also contributed their time and energy, alongside other community volunteers helping with additional projects around the park.

History: Mossbrucker Park was dedicated in honor of Sgt Timothy M. Mossbrucker who was killed in the line of duty in 1995. The park name was officially adopted on March 26, 1996.

Back to top

Completed in 2024

Foothills Golf Course – Clubhouse

Completed: April 2024

Improvements Description: Constructed a new clubhouse featuring sweeping interior views of the Colorado Rocky Mountains, a larger proshop, expanded lounging areas, restaurant and terrace with an indoor-outdoor bar, new accessible entry, parking lot improvements and addition, indoor storage space for golf carts.

Community Outreach:

  • Virtual Community Meeting was held via Zoom on June 1, 2021.
  • Survey with concept plans was provided for community input. Feedback from survey was utilized for a revised concept plan.
  • Concept plans and design rendering were provided to the community.

History: Foothills built the golf course in 1971.

Back to top

Overhead drone shot of the new Foothills Golf Course Clubhouse building and golf course property in background.

Hoida Park

Completed: Spring 2024

Improvements Description: Replaced irrigation, improved entry walk, site improvements, sanolet enclosure, new trees, turf conversion in some parts of the park to non-irrigated grasses for water conservation.

Community Outreach:

  • Concept Plans were provided to the community.

History: The park was acquired in 1972.

Back to top

Lakehurst Park

Completed: Fall 2024

Improvements Description: New playground, new trail connection to Harriman Lake Park and new playground, new trees, replaced irrigation system, new benches, concrete performance stage and turf conversation in some parts of the park to non-irrigated grasses for water conservation.

Community Outreach:

  • Virtual Community Meeting was held via Zoom on Wednesday, March 24, 2021.
  • During previous engagements with the community, the concrete apron that borders sections of Lakehurst Park has been a primary topic of discussion.  Due to some complicated ownership issues, Foothills is not able to remove or repair the existing concrete apron.  In summary, the concrete apron is partially on Foothills property and partially on the property of each residence that backs up to the park.  The portion of concrete apron on private property is not owned or managed by Foothills, but rather, is owned by over 50 private homeowners. While Foothills remains committed to engaging with the neighborhood about the future of the concrete apron, it is an issue that will likely take a longer amount of time to resolve.  With this in mind, Foothills plans to move forward with improvements to Lakehurst Park in 2024.
  • A community survey was provided April 1-15, 2022 to provide project background information and obtain community input.
  • An open house for Lakehurst Park Improvements was held June 1, 2022 to share survey results and seek input on concept plans developed from the results of the community survey.
  • A community survey was provided August 12-26, 2022 to obtain community selection on a final concept plan.
  • Concept plans for the park and for the playground were provided to the community.

History: Foothills acquired the park in sections from 1963-1966.

Back to top

Meadows Golf Club – Putting Green practice area

Completed: Spring 2024

Improvements: Putting green practice area was increased in size to accommodate more use and also improved sloping issues.  Thank you to the Meadows Mens Club for their generous donation to the project.

Back to top

Practice putting green at Meadows Golf Club with the clubhouse and portions of the golf course in the background.

West Laurel Park

Completed: Spring 2024

Improvements Description: Replaced irrigation, shade added to playground, new trees, sanolet enclosure, site improvements.

Community Outreach:

  • Virtual Community Meeting was held via Zoom on January 24, 2022.
  • A community survey was provided April 1-15, 2022 to provide project background information and obtain community input.
  • Concept plans were provided to the community.

History: A portion of this park was dedicated to Foothills in the early 1980s. A second parcel was leased to Foothills from Jefferson County Open Space about the same time. The park was originally called Columbine Knolls South Park.

Back to top

Westbury Park

Completed: Spring 2024

Improvements Description: New playground installed in July 2023. Replaced irrigation, removed the old playground, replaced tables and grill at the shelter, added benches by the new playground, planted new trees, turf conversion in some parts of the park to non-irrigated grasses for water conservation.

Community Outreach:

  • A community survey was provided May 11-25, 2022 to provide project background information and obtain community input.
  • Virtual Community Meeting was held via Zoom on October 18, 2022.
  • Revised Concept Plans were provided to the community for feedback.
  • Community Survey for Playground April 3-17, 2023 to vote on playground concept.
  • Playground Concept Plans were provided to the community for feedback.

History: This park was originally developed and dedicated to Foothills in 1978 by the developer of the adjacent Foothill Green Subdivision.

Back to top

Willow Creek Park

Completed: Spring 2024

Improvements Description: Replaced irrigation, replaced playground equipment and surfacing, planted new trees, turf conversion in some parts of the park to non-irrigated grasses for water conservation.

Community Outreach:

  • Park Site Concept Plans and Playground Concept Plans were provided to the community for feedback.

History: This park was dedicated to Foothills in 1985.

Back to top

Completed in 2023

6th Avenue West Outdoor Pool

Completed: Fall 2023, pool opened to the public on May 25, 2024

Improvements Description: Constructed a new bathhouse with all new mechanical, filtration, plumbing and heating systems, new accessible parking and entry, new zero-depth wading pool with play features and water sprays, added floating features to the lap pool to improve water play opportunities when not being used for competitive or lap swimming, added a drop slide and flume slide to the existing diving pool, new concrete pool decks, new shade structures, seating and lawn area.

Community Outreach & Project Information:

  • An initial Conceptual Planning Survey was provided to the community and closed in late June 2021.  Community feedback was provided to the design team.  A second survey was sent to the community and closed in early September 2021.
  • Concept plans, updated plans and design rendering were provided to the community.

Park History: In 1974 Ridgewood Realty financed the construction of the parking lot, pool, and tennis courts. Foothills Park staff completed the landscaping and irrigation system the same year.

6th Avenue West Outdoor Pool site showing people playing in the water and on a water play structure.

Columbine West Outdoor PoolPark

Completed: Fall 2023, pool opened to the public on May 25, 2024

Improvements Description: Constructed a new bathhouse with all new mechanical, filtration, plumbing and heating systems, new accessible parking and entry, added a new zero-depth entry activity area onto the existing lap pool with a play feature, in-ground water sprays and other spray features, added floating features to improve water play opportunities in non-lap lane areas, added a drop slide and diving tower to the existing diving pool, new concrete pool decks, new shade structures and seating areas.

Community Outreach & Project Information:

  • An initial Conceptual Planning Survey was provided to the community and closed in late June 2021.  Community feedback was provided to the design team. A second survey was sent to the community and closed in early September 2021.
  • Concept plans, updated plans and design rendering were provided to the community.

Park History: This park was constructed in 1973-74 with funding assistance from Ridgewood Realty.

Columbine West Outdoor Pool site showing people playing in the water and on a water play structure.

Completed in 2022

Clement Park – Sport Court Complex

Completed: Summer 2022

Improvements Description: Reconfigured sports court area to resurface one existing tennis court, add two new tennis courts and add 10 new pickleball courts – lighting was added to these 13 courts. Additional improvements include: replaced playground, replaced concrete around restrooms, replaced irrigation, new sod, improved drainage, added ADA access from parking lot, trees will be planted in fall 2022.

History: The site now known as Clement Park was part of the Grant Family Ranch and was purchased from the Grant Family by Jefferson County Open Space for use as a park. In 1987, Jefferson County Open Space developed Clement Park with funds from the county-wide Open Space Tax. In 1989, the park was leased to Foothills Park & Recreation District for management purposes, and was deeded to Foothills in 2018.  As part of the Clement Park Redevelopment Master Plan, several other improvements were completed during a multi-year process from 2016-2019.

Back to top

Columbine Hills Park

Completed: Summer 2022

Improvements Description: Replaced irrigation

History: Foothills acquired the land in 4 separate parcels beginning in 1962. Columbine Hills Park is one of the oldest Foothills parks.

Back to top

Columbine Sports Park

Completed: Summer 2022

Improvements Description: Replaced irrigation

History: The athletic components of the site were developed in 1989-90 in part with a $47,000 gift from Columbine Sports.

Back to top

Ridge Recreation Center

Completed: May 2022

Improvement Description: New Splash Pad added to the outside sun deck located outside the Activity Pool providing an indoor/outdoor experience to the pool.

History: Foothills opened this facility in 2003.

Back to top

Victory Park

Completed: 2022

Improvement Description: Replaced irrigation, replaced playground, new concrete walk, half basketball court, new site amenities, planted new trees, turf conversion in some parts of the park to non-irrigated grasses for water conservation.

Community Outreach:

  • My Dream Playground Meeting was held January 19, 2022.
  • Concept plans were provided to the community for feedback.

History: Foothills acquired the park in 1982.

Back to top

Westbury Greenbelt

Completed: 2022

Improvement Description: Replaced irrigation, trail repairs, planted new trees, turf conversion in some parts of the park to non-irrigated grasses for water conservation.

Community Outreach:

  • Concept plans were provided to the community for feedback.

History: The developer of the Foothills Green Subdivision built this greenbelt and dedicated it to Foothills in 1976.

Back to top

Westfield Park

Completed: 2022

Improvement Description: Replaced irrigation, replaced playground, added ADA access to playground, added stone seatwall, concrete plaza with new shelters, new site amenities, planted new trees, turf conversion in some parts of the park to non-irrigated grasses for water conservation.

Community Outreach:

  • My Dream Playground Meeting was held January 20, 2022.
  • Meeting was held February 16, 2021.
  • Revised schematic plans were provided to the community for feedback.

History: Foothills acquired the park in 1972.

Back to top

Completed in 2021

Completed in 2020

Completed in 2019

Completed in 2018

Back to top